June 2020
.jpg)
.jpg)
%20(002).jpg)
06-29-20 Athletic Field Groundbreaking Ceremony with Board of Education, Superintendent, Director of Athletics, Facilities and School Safety and representatives from French Associates, AUCH Construction and Midwest Landscaping Group, Inc.
06-29-20 Superintendent and representatives from French Associates walk-through middle school and high school to determine flooring, door/hardware replacement and validate scope of work.
06-24-20 Superintendent, Director of Athletics, Facilities and School Safety, and and representative from Keifer Floors met to discuss high school auxillary gymnasium and weight room floors.
06-23-20 Bond Team Meeting with Superintendent, Director of Facilities and School Safety, Auch Construction and French Associates to review drawings and scope of work for middle school and high school.
06-22-20 Board of Education approved contracts for the following bid packages for the Elementary Addition and Renovation Project:
Proposal A: Selective Structure Demolition to DKI International, Inc. ($109,900)
Proposal B: Cast-in Place Concrete – Foundations to Novi Wall, Inc. ($100,434)
Proposal C: Cast-in Place Concrete – Flatwork to Metropolitan Concrete ($145,295)
Proposal D: Masonry to Davenport Masonry ($849,700)
Proposal E: Structural Steel, Miscellaneous Steel, and Metal Fabrications to Judd Industrial Contracting, Inc. ($138,950)
Proposal F: Carpentry and Millwork to Wally Kosorski & Company, Inc. ($191,910)
Proposal G: Roofing and Metal Wall Panels to ESKO Roofing & Sheet Metal ($343,800)
Proposal H: Glass & Glazing, Storefront, Aluminum/FRP Doors to Madison Heights Glass Company, Inc. ($193,375)
Proposal I: HM and Wood Doors, Frames and Hardware to La Force, Inc. ($91,165)
Proposal J: Gypsum Wall Assemblies to Acoustic Ceilings & Partitions Company ($86,920)
Proposal K: Hard Tile to Michielutti Brothers, Inc. ($44,100)
Proposal L: Acoustic Work to Acoustic Ceilings and Partitions ($162,531)
Proposal M: Resilient Flooring and Carpet to Shock Brothers Flooring Coverings, Inc. ($303,500)
Proposal N: Epoxy Floor Repairs to GV Painting, LLC. ($10,749)
Proposal O: Painting to GV Painting, LLC. ($93,577)
Proposal P: Visual Display Surfaces to Cig Jan Products ($15,522)
Proposal Q: Signage to DMP Sign Company ($7,000)
Proposal S: Institutional Casework to Architectural Systems Group, LLC. ($170,510)
Proposal T: Plumbing to Contrast Mechanical ($199,000)
Proposal U: HVAC Mechanical to Contrast Mechanical ($1,380,000)
Proposal V: Electrical to Sawyer Services, Inc. ($882,700)
Proposal W: Site Work/Utilities to Teltow Contracting, Inc. ($140,000)
Proposal X: Vinyl Coated Chain-Link Fence and Gates to RMD Holdings, LTD ($13,925)
06-19-20 Interviews conducted at 10:00am with contractor who bid on the Elementary Additions and Renovations project.
06-16-20 Review MS Roofing specifications with Superintendent, Auch Construction, French and Associates.
06-15-20 Review Richmond Building and Site Drawings with the Local Emergency Response Team (e.g. Richmond-Lenox EMS, Fire ad Police Department, and City of Richmond) with Superintendent and Director of Athletics, Facilities and School Safety.
06-12-20 Interviews conducted at 9:00am, 9:30am, 10:00am, 10:30am, 11:00am, 1:00pm, and 1:30pm with contractors who bid on the Elementary Additions and Renovations project.
06-11-20 Interviews conducted at 8:30am, 9:00am, 10:00am, 1:00pm, 2:00pm, 3:00pm, 3:30pm and 4:00pm with contractors who bid on the Elementary Additions and Renovations project.
06-10-20 Interviews conducted at 8:30am, 9:00am, 10:00am, 11:00am, 1:30pm, 2:30pm, 3:30pm and 4:30pm with contractors who bid on the Elementary Additions and Renovations project.
06-09-20 Interviews conducted at 1:00pm, 2:30pm, and 3:00pm with contractors who bid on the Elementary Additions and Renovations project.
06-09-20 Bond Team Meeting with Superintendent, Director of Facilities and School Safety, Auch Construction and French Associates to review drawings and scope of work for middle school and high school.
06-08-20 Superintendent presented an update on bond projects to the Board of Education and listening audience, via Zoom. Presentation included conceptual drawings of the parking lots and roads throughout the District as well as an update on the Athletic Complex project.
06-08-20 Interviews conducted at 9:00am, 10:00am, 11:00am, 1:30pm, and 2:30pm with contractors who bid on the Elementary Additions and Renovations project.
06-05-20 Parking Lot and Road overview meeting was held, via Zoom, with the City Manager from the City of Richmond.
06-04-20 Bid Openings regarding the Elementary Additions and Renovations. Auch Construction and District Core Bond Team conducted the bid openings at 2:00pm. 106 Bid were received by the 2:00pm deadline.